MGT 440 Topic 7 earned value status report example

Project Management Grand Canyon University Free custom sample in 24 to 48h

This MGT 440 Topic 7 sample paper uses earned value to report where a credit union's contact center move stands after twelve weeks. It was prepared for GCU MGT 440, Project Management, catalog code MGT-440, in the Grand Canyon University BS in Business Management program. Planned value is $72,000, earned value $63,000 and actual cost $75,600 against a $180,000 budget. Schedule and cost variances, a schedule index of 0.875 and a cost index of about 0.83 follow. The forecast of $216,000 exceeds budget plus remaining reserve by $24,000. A direct check of the critical path finds build-out four days behind, and $24,000 in scope deferrals are proposed.

CourseMGT 440 Project Management
TopicTopic 7
Paper typeEarned value report
LengthAbout 970 words, 4 pages
FormatAPA 7 student paper
SchoolGrand Canyon University (GCU)
ProgramBS in Business Management
UpdatedOctober 2026

Free sample paper for MGT 440 Topic 7

1

Behind and Over, by How Much and What to Cut: An Earned Value Status Report for a Contact Center Relocation at Week Twelve

[Author Name]

Colangelo College of Business, Grand Canyon University

MGT-440: Project Management

Topic 7 Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe title gives the headline in plain words and promises the two things a sponsor needs from a status report, the size of the problem and a recommendation. The credit union and every figure are an illustrative composite; the sources are real.
2

Behind and Over, by How Much and What to Cut: An Earned Value Status Report for a Contact Center Relocation at Week Twelve

Three Figures and What They Mean

At the end of week twelve, the credit union's contact center relocation had planned to complete $72,000 of work, had completed work worth $63,000 by the plan's own valuation and had spent $75,600 to do it. In plain terms: the project is behind schedule and over budget, and if nothing changes it will finish about $24,000 beyond what the budget and remaining reserve can cover. This report sets out the calculation, checks the schedule against the critical path and recommends how to close the gap. All figures are illustrative.

What this page is doingThe report opens with the three figures and a one-sentence translation, because a sponsor reading only the first paragraph should still know the project's condition.
3

The Calculation

Table 1

Earned Value Measures at Week Twelve

MeasureFormulaValueMeaning
Planned value (PV)From the baseline$72,000Work scheduled to date
Earned value (EV)Budgeted cost of work completed$63,000Work actually done
Actual cost (AC)From the ledger$75,600Money spent
Schedule varianceEV minus PV-$9,000Behind schedule
Cost varianceEV minus AC-$12,600Over budget
Schedule performance indexEV / PV0.875Doing 87.5 cents of planned work per dollar scheduled
Cost performance indexEV / AC0.83Getting about 83 cents of work per dollar spent
Estimate at completionBAC / CPI$216,000Forecast final cost if efficiency continues

Earned value management sets three numbers side by side: what the plan said should be done by now, priced at budget; what has actually been finished, priced the same way; and what the finished work really cost (Fleming & Koppelman, 2010). Table 1 derives the standard measures from them, against a budget at completion of $180,000.

A cost index below 1.0 means each dollar spent has bought less work than planned. A schedule index below 1.0 means less work has been completed than the plan called for by this date. Both are below 1.0 here, so the project is getting less for its money and getting it later.

What the Forecast Says

If the project continues to spend at its current efficiency, it will cost about $216,000 to finish, $36,000 more than the $180,000 budget. The sponsor's management reserve has $12,000 remaining, so the budget plus reserve is $192,000. The forecast exceeds that by $24,000.

The forecast assumes cost efficiency stays at 0.83 for the rest of the project. That may be too pessimistic or not pessimistic enough. Most of the overrun so far came from build-out, where the contractor found old wiring behind the walls that had to be removed, adding labor that will not recur. On the other hand, research on earned value has found that the cost performance index tends to stabilize early in a project and rarely improves much afterward, which argues against assuming the rest of the work will be cheaper (Lipke et al., 2009). This report therefore treats the $24,000 gap as real and plans to close it.

Other forecasting formulas exist. One assumes the remaining work will be done at the budgeted rate, which would give a final cost of about $192,600, just above budget plus reserve. The report uses the more cautious figure because the cause of the overrun, old building conditions, could recur on the north side of the floor.

Checking the Critical Path Directly

The schedule performance index of 0.875 says the project has done less work than planned, but it does not say whether the delay affects the end date. Work behind schedule on an activity with float may not matter; work behind on the critical path does. So the report checks the critical path directly.

Build-out and cabling, on the critical path, is four days behind its baseline, because of the old wiring. Network installation cannot start until build-out finishes, so the cutover date has moved from October 10 to October 16 in the current schedule. That still falls before the October 24 deadline, leaving eight days of margin rather than the original fourteen. Furniture ordering, off the critical path, is also behind but within its float. The earned value figures and the critical path tell a consistent story: the project is late on the work that matters, but not yet late enough to threaten the lease date.

Margin of eight days is still useful, but it is shrinking. If build-out slips another eight days, the project would have no room left before the lease deadline. The project manager has asked the contractor for a daily progress note until build-out is complete.

What this page is doingThe report does not rely on the schedule index alone; it checks the critical path, which is what actually determines whether the deadline is at risk.
4

Recommendation

The report recommends scope reductions totaling $24,000, so that the forecast cost falls within budget plus reserve without touching the date. Each item was discussed with the contact center manager and is a deferral rather than a cancellation.

1. Defer the new huddle room's video equipment until next fiscal year, saving $9,500. The room will be built, but the screen and camera will be added later.

2. Reuse the existing supervisor desks instead of buying new ones, saving $6,800.

3. Defer replacing the acoustic panels on the north wall, which the new layout makes less necessary, saving $4,700.

4. Reduce the planned agent training on the new floor from two sessions to one, with the second replaced by a short video, saving $3,000 in overtime.

These reductions total $24,000. The sponsor is asked to approve them at this status meeting through the change process. If they are approved, the next report will show whether cost efficiency has held, and the project manager will continue to track build-out against the critical path weekly until network installation begins. Reporting the gap now, while it can still be closed by small deferrals, is the purpose of tracking earned value (Project Management Institute, 2021).

The deferrals were chosen because none of them affects the acceptance criteria or the cutover date. Each can be funded later from operating budgets without reopening the project.

References

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

The MGT-440 Topic 7 assignment instructions

MGT-440 Topic 7 asks students to report project performance using earned value management. A table of figures without interpretation, or a narrative without figures, will not serve a sponsor. The prompt rewards a report that opens with its main figures and their meaning, derives variances, performance indexes and a forecast at completion, and compares the forecast with the money available. Students should check the schedule against the critical path, since a schedule index alone cannot show whether the deadline is at risk, and close with a recommendation the sponsor can approve, stating its cost effect and how progress will be tracked. Every figure should be labeled as illustrative where the case is composite.

How the MGT-440 Topic 7 example is put together

The report opens with three figures and a plain summary of the project's condition. Table 1 derives the standard earned value measures with formulas and meanings. A section explains the forecast at completion and why the $24,000 gap is treated as real, citing research on the stability of the cost index. The critical path is then checked directly, showing build-out four days behind and the cutover still eight days ahead of the deadline. Four scope deferrals totaling $24,000 are listed with their savings, and the sponsor is asked to approve them through the change process. The deferrals were chosen so that none touches an acceptance criterion.

Reading the MGT 440 Topic 7 rubric

Faculty grading the earned value report reward correct calculations presented so a sponsor can follow them. Strong reports explain what each index means, compute the forecast at completion and compare it with budget plus reserve. Credit goes to questioning the forecast's assumption and to checking the critical path rather than relying on the schedule index. The rubric values a recommendation sized to close the gap exactly, with each item costed. The highest band asks for a specific decision and states how the next report will track progress. Reports that list figures without a recommendation usually lose points. Formulas shown beside each figure let a reader check the arithmetic.

MGT 440 Topic 7 help: mistakes that cost marks

Earned value reports can be marked wrong on the figures, and the classic error is comparing actual cost with planned value. Doing that here suggests the project is only 3,600 dollars over, when the true cost variance, earned value minus actual cost, is minus 12,600. Reports reading an index below 1.0 as favorable, or treating a negative variance as savings, have inverted the result, and every conclusion follows the inversion. Forecasts produced without stating the method cannot be checked, since different formulas give different answers. Papers reporting indices with no interpretation leave a sponsor holding numbers without meaning. Status reports stopping at the forecast, without saying which constraint absorbs the overrun, have measured the problem and handed it back unsolved.

Get an MGT-440 Topic 7 example written to your instructions

Send the MGT-440 Topic 7 instructions, the rubric in your classroom and the baseline or status data the assignment supplies. We write a custom example to those criteria, with variances and indices derived and explained, a forecast with its method stated, the critical path checked and a decision put to the sponsor, in 24 to 48 hours. The first one is free.

More MGT 440 papers and BS in Business Management samples

MGT 440 Topic 7 questions, answered

What is the difference between planned value and earned value?

Planned value is the budgeted cost of the work scheduled to be done by the status date. Earned value is the budgeted cost of the work actually completed by then. Comparing them shows schedule performance in dollar terms, and comparing earned value with actual cost shows cost performance. Setting actual cost against planned value produces a figure that measures neither.

Which forecast formula should the report use?

The course text usually specifies one. Dividing budget at completion by the cost index assumes current cost performance continues, which is the common default and the one the example uses. Other versions assume the remaining work will go to plan, or blend cost and schedule indices. Stating the formula lets a reader check the figure and argue with the assumption.

Why check the critical path if earned value covers schedule?

Because schedule indices aggregate everything in dollars, so progress on non-critical work can offset a delay on critical work. A project can show a reasonable index while the activity controlling the finish date slips. Checking the critical path directly answers the question the index cannot, which is whether the end date itself is at risk.

Where can I find a free MGT 440 Topic 7 sample paper?

The week-twelve report is on this page with all of its parts: the three figures, the calculation table, the forecast, the critical path check and the recommended deferrals. Send your project's planned value, earned value and actual cost, and a free report can be prepared from them.

How is the forecast calculated in MGT 440 Topic 7?

The budget at completion of $180,000 is divided by the cost performance index of about 0.83, giving $216,000. That exceeds the $192,000 of budget plus remaining reserve by $24,000.