BUS 660 Topic 8 project scheduling recommendation example

Quantitative Methods Grand Canyon University Free custom sample in 24 to 48h

This BUS 660 Topic 8 sample paper schedules a composite bakery's new production line against a grocery launch 32 days away. It completes GCU BUS 660, Quantitative Methods, catalog code BUS-660, in Grand Canyon University's MBA. Forward and backward passes give a 36-day project with A-D-F-G critical and slack of 1, 10 and 13 days elsewhere. Crashing the cheapest critical day, trial bakes at 400 dollars, makes a second path critical, so equipment delivery is then cut three days at 500 a day. The deadline costs 1,900 dollars. Against 18,000 dollars of forfeited orders, the cost is worth paying. The critical path is rechecked after every purchase of time.

CourseBUS 660 Quantitative Methods
TopicTopic 8
Paper typeProject scheduling recommendation
LengthAbout 980 words, 2 pages
FormatAPA 7 student paper
SchoolGrand Canyon University (GCU)
ProgramMBA
UpdatedOctober 2026

Free sample paper for BUS 660 Topic 8

1

Buy the Cheapest Days First, Then Check the Path: Scheduling and Crashing a Bakery's New Production Line to Meet a Grocery Launch

[Author Name]

Colangelo College of Business, Grand Canyon University

BUS-660: Quantitative Methods

Topic 8 Project Scheduling Recommendation

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe title states the crashing rule and the step most analyses forget. The bakery and every figure are a composite; the sources are real.
2

Buy the Cheapest Days First, Then Check the Path: Scheduling and Crashing a Bakery's New Production Line to Meet a Grocery Launch

The Project and the Deadline

A composite regional bakery is installing a new production line to supply a grocery chain whose launch is 32 days away. The project manager wants to know whether the line can be ready in time and, if not, which activities to speed up at the lowest cost. This paper builds the project network from the activities and their predecessors, identifies the critical path by computing early and late times, and then treats crashing, speeding up activities at extra cost, as a purchase. Figures are illustrative; durations are in working days.

Activities and Relationships

The network follows from the relationships among activities, not from a preferred layout.

Table 1

Project Activities, Durations and Crash Costs

ActivityDescriptionPredecessorsNormal daysCan crash toCrash cost per day saved
AOrder and receive equipmentNone2016500 dollars
BPrepare floor and utilitiesNone107800 dollars
CHire and train staffNone1515Cannot crash
DInstall equipmentA, B861,200 dollars
EHealth inspectionD55Cannot crash
FTrial bakesC, D64400 dollars
GLaunch preparationE, F22Cannot crash

Early and Late Times

The forward pass computes each activity's earliest start and finish. A, B and C start at day 0 and finish at days 20, 10 and 15. D cannot start until both A and B are done, so it starts at day 20 and finishes at 28. E then runs from 28 to 33; F waits for D and C and runs from 28 to 34. G waits for E and F, starting at 34 and finishing at 36. The project takes 36 days at normal durations, four days too long.

The backward pass computes each activity's latest start and finish without delaying the project. Slack, the difference between latest and earliest start, is zero for A, D, F and G, so they form the critical path, A-D-F-G, 36 days. E has 1 day of slack, B has 10 and C has 13. The critical path is identified by these calculations rather than by inspecting which chain looks longest, and the slack figures matter: staff and contractors can safely be moved from B and C, which have room, to help activities on the critical path (Render et al., 2018).

Crashing as a Purchase

Kelley and Walker (1959) developed critical-path scheduling partly to find the least-cost way to shorten a project. The rule is to buy the cheapest day on the critical path, then recompute the critical path before buying the next, because shortening one path can make another critical. That recheck is the step most analyses forget.

Day 1: the only critical path is A-D-F-G. The cheapest activity on it is F, at 400 dollars. Crash F by one day; the project falls to 35 days. Now recheck: path A-D-E-G is also 35 days, because E's one day of slack is gone. Two paths are critical.

Days 2 to 4: any further day saved must shorten both A-D-F-G and A-D-E-G. Crashing F alone would no longer help, because A-D-E-G would still take 35. The activities on both paths are A, at 500 dollars a day, and D, at 1,200. A is cheaper, so crash A by three days. Both paths fall to 32 days.

The project now finishes in 32 days at an added cost of 400 plus 3 times 500, or 1,900 dollars. A check of every combination of crashable days confirms 1,900 dollars as the minimum cost of meeting 32 days. Crashing A alone by four days would also reach 32 but cost 2,000, and crashing F by two days first, without rechecking, would waste the second day.

Is Meeting the Deadline Worth 1,900 Dollars?

Crashing is a purchase, so it should be compared with what it buys. The grocery chain's contract allows the bakery to start supplying at launch or forfeit the first month's orders, worth about 18,000 dollars in contribution. Spending 1,900 to protect that is plainly worthwhile. If the contract instead allowed a late start with a small penalty, say 1,000 dollars, the bakery would be better off finishing in 36 days and paying it. The network tells the manager what the deadline costs; the contract tells the manager what the deadline is worth.

Reading the Result

After crashing, two paths are critical, A-D-F-G and A-D-E-G: every one of A, D, E, F and G has zero slack, and B and C still have 7 and 10 days. The project is fragile: any delay in equipment delivery, installation, inspection or trial bakes will miss the launch. The manager should monitor those activities daily, ask the equipment supplier for a firm delivery date with a penalty for lateness, and schedule the health inspection in advance so it cannot slip.

Why Crashing Follows the Cheapest Days

Kelley (1961) set out the mathematical basis for trading time against cost on a project network: shorten the activities on the critical path whose extra cost per day is lowest, and recheck the critical path after each step, since shortening one path can make another critical. The bakery's schedule follows that rule, which is why the analysis rechecks the network after the first purchase and finds a second critical path.

Conclusion

The network shows a 36-day project against a 32-day deadline, with A-D-F-G critical. Buying the cheapest days first and rechecking the critical path after each purchase meets the deadline for 1,900 dollars: one day from trial bakes and three from equipment delivery. Without the recheck, the analysis would have overspent or failed to shorten the parallel path that became critical. The same method applies whenever the launch date moves: recompute the network, find the new critical paths and buy the cheapest days that shorten all of them.

References

Kelley, J. E. (1961). Critical-path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296-320. https://doi.org/10.1287/opre.9.3.296

Kelley, J. E., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference (pp. 160-173). Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318

Render, B., Stair, R. M., Hanna, M. E., & Hale, T. S. (2018). Quantitative analysis for management (13th ed.). Pearson.

Reading the GCU BUS 660 Topic 8 instructions

Topic 8 brings BUS-660 to a close by asking MBA students to schedule a project and recommend how to meet a deadline. Strong recommendations build the network from activities and predecessors, find the critical path by computing early and late times, and report slack for every activity. Students should treat crashing as a purchase, buying the cheapest day on the critical path and rechecking the critical path after each day, confirm the minimum cost, weigh the cost against what the deadline is worth and plan how to manage the now-fragile schedule. Students should also recheck the critical path after each crash, since a second path can become critical.

How this BUS 660 Topic 8 example is built

The finished example finds the constraint and then prices relieving it. Activities are listed with their durations and their predecessors, and the network follows from those relationships rather than from a preferred layout. The critical path is identified by computing early and late times rather than by inspecting the longest looking chain, and slack is reported for every activity, since the non critical ones are where resources can safely be moved from. Crashing is then treated as a purchase: each compressible activity has a cost per day saved, and the example buys the cheapest days first, checking after each whether the critical path has changed, which is the step most analyses forget.

BUS 660 Topic 8 rubric: what Excellent looks like

Faculty reward crashing that rechecks the path after each purchase. An Excellent paper tables seven activities with predecessors and crash costs and computes a 36-day critical path. Credit goes to reporting slack for every activity and moving staff from B and C. The rubric values crashing trial bakes first, finding the second path critical and then crashing equipment, following Kelley and Walker, for 1,900 dollars. Strong papers confirm the minimum by enumeration. Top marks go to weighing 1,900 dollars against 18,000 of forfeited orders. Papers that stop crashing when the next day costs more than the deadline is worth, and say so, show crashing treated as a purchase decision rather than an exercise in shortening.

BUS 660 Topic 8 help before you submit

Identifying the critical path by looking at the network rather than computing it is unreliable on anything but a trivial project, and it is the shortcut that produces wrong answers here. A second failure is crashing without rechecking, which spends money compressing a path that stopped being critical two purchases ago. Papers lose marks for reporting a schedule with no slack figures, since slack is what tells a manager where flexibility exists. Crashing every activity that can be crashed ignores that only the critical path affects the finish date. Ending with a network diagram and no recommendation misses the closing requirement, which asks for a defended decision about how much time to buy and at what price.

Get a BUS-660 Topic 8 example written to your instructions

Send the BUS-660 Topic 8 problems and the rubric from your classroom, with the activity list and crash costs your section supplied. We write a custom example to those criteria, with the critical path computed rather than inspected, slack reported throughout, crashing bought incrementally and the path rechecked at each step, in 24 to 48 hours. The first is free.

More BUS 660 papers and MBA samples

BUS 660 Topic 8 questions, answered

Why compute the critical path instead of looking for it?

Because on any realistic network the longest path is not obvious and parallel chains can differ by a day. Computing early and late start times gives you slack for every activity, and the critical path falls out as the activities with none. It also gives you the slack figures you need afterward, so the computation produces two useful outputs rather than one.

Which activities should I crash?

Only ones on the critical path, and among those the cheapest per day saved. Compressing an activity with slack changes nothing about the finish date and wastes the money entirely. Buy one increment at a time and recompute, because as soon as the critical path shortens enough, another path becomes critical and the cheapest useful purchase changes.

When should I stop crashing?

When the next day costs more than finishing a day earlier is worth. That requires knowing the value of early completion, whether it is a contractual bonus, avoided overhead or a market window, and comparing it against the marginal crash cost. Crashing until the schedule cannot compress further is an engineering answer; stopping where the value runs out is the business one.

Where can I find a free BUS 660 Topic 8 sample paper?

The scheduling recommendation is shown here complete: the project and deadline, activities, early and late times, crashing as a purchase, whether the deadline is worth the cost, reading the result and the conclusion. Bring your project network and we will schedule it at no charge.

Why recheck the critical path in BUS 660 Topic 8?

Cutting trial bakes by a day made the inspection path critical too, so further days had to come from equipment delivery, which shortens both paths. Without the recheck, money is wasted on one path.