| Course | MGT 440 Project Management |
|---|---|
| Topic | Topic 4 |
| Paper type | Critical path calculation |
| Length | About 990 words, 4 pages |
| Format | APA 7 student paper |
| School | Grand Canyon University (GCU) |
| Program | BS in Business Management |
| Updated | October 2026 |
Free sample paper for MGT 440 Topic 4
Forty Days Through Build-Out: The Critical Path for a Contact Center Relocation, With a Three-Point Estimate, Both Passes and the Float on the Other Path
[Author Name]
Colangelo College of Business, Grand Canyon University
MGT-440: Project Management
Topic 4 Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Forty Days Through Build-Out: The Critical Path for a Contact Center Relocation, With a Three-Point Estimate, Both Passes and the Float on the Other Path
The Question
The contact center relocation must finish its cutover before the lease ends. The project manager needs to know how long the core work will take, which activities determine that length and how much slack the others have. This calculation answers those questions for the six main activities in the work breakdown structure. All durations are in working days and are illustrative estimates agreed with the activity owners.
Activities, Durations and Predecessors
Table 1
Activities for the Core Relocation Work
| Activity | Description | Duration | Predecessors |
|---|---|---|---|
| A | Layout approval | 5 | None |
| B | Build-out and cabling | 20 | A |
| C | Furniture and phone equipment ordering and delivery | 15 | A |
| D | Network and telephony installation | 10 | B |
| E | Furniture installation | 5 | C |
| F | Testing and cutover | 5 | D, E |
Table 1 lists the six activities. Build-out and cabling is the most uncertain, because it depends on the landlord-approved electrician and on what the contractor finds behind the third-floor walls, so its duration uses a three-point estimate.
The Three-Point Estimate for Build-Out
The contractor gave three estimates for build-out and cabling: an optimistic 15 days if no surprises appear, a most likely 19 days and a pessimistic 29 days if the electrical upgrade runs late or the walls need extra work. The weighted formula developed for program evaluation and review gives the most likely value four times the weight of either extreme (Malcolm et al., 1959): (15 + 4 x 19 + 29) / 6 = 120 / 6 = 20 days.
The estimate is pulled above the most likely value because the pessimistic case is further from it than the optimistic case is. That asymmetry is typical of construction work: there are more ways for it to run late than early. The same formula gives a standard deviation of 29 minus 15, divided by 6, or about 2.3 days, which indicates how much the build-out duration could reasonably vary.
The Forward Pass
Table 2
Forward Pass
| Activity | Early start | Duration | Early finish |
|---|---|---|---|
| A | 0 | 5 | 5 |
| B | 5 | 20 | 25 |
| C | 5 | 15 | 20 |
| D | 25 | 10 | 35 |
| E | 20 | 5 | 25 |
| F | max(35, 25) = 35 | 5 | 40 |
The forward pass works from the start of the project to the end, finding the earliest each activity can start and finish. Each activity can begin only when the last of its predecessors is done, and it ends its duration later. Day 0 is the start of the project.
The project's earliest finish is day 40. Testing and cutover cannot start until both network installation and furniture installation are done, and network installation finishes later, at day 35.
Furniture installation could finish as early as day 25, but that gains nothing, because testing must wait for the network work on the longer path. This is the first sign of which path controls the project.
The Backward Pass and Float
Table 3
Backward Pass and Total Float
| Activity | Late finish | Late start | Total float |
|---|---|---|---|
| F | 40 | 35 | 0 |
| D | 35 | 25 | 0 |
| E | 35 | 30 | 10 |
| B | 25 | 5 | 0 |
| C | 30 | 15 | 10 |
| A | min(5, 15) = 5 | 0 | 0 |
The backward pass works from the project's finish, day 40, back to the start, finding how late each activity could begin and end while still letting the cutover happen on day 40. An activity's late finish is the earliest late start of its successors; its late start is late finish minus duration. Subtracting each early start from the matching late start gives the activity's total float.
Activities with zero float leave no room for delay. Furniture ordering and installation can each slip up to ten days, but the float is shared along that path: if ordering uses five days of it, installation has only five left.
The Critical Path
Two paths run through the network. The path A, B, D, F totals 5 + 20 + 10 + 5 = 40 days, and every activity on it has zero float. The path A, C, E, F totals 5 + 15 + 5 + 5 = 30 days, and furniture ordering and installation each have 10 days of float. The critical path is therefore layout approval, build-out and cabling, network and telephony installation, and testing and cutover. Any delay on those four activities delays the cutover day for day. The critical path method was developed to identify exactly this chain, so that management attention goes to the activities whose timing determines the project's end (Kelley & Walker, 1959).
The critical path can change. If furniture delivery slipped by more than ten days, the furniture path would become longer than the network path, and the critical path would move to it. Recalculating at each status meeting keeps the project manager watching the right activities.
What the Calculation Means for the Project
Three implications follow. First, the project manager's attention belongs on build-out. It is the longest and most uncertain activity on the critical path, and its pessimistic estimate alone would add nine days. The electrical upgrade that precedes it should be booked early, and the project manager should check its progress weekly.
Second, the furniture path has ten days of float, which means furniture ordering can be delayed up to ten days without affecting the cutover. That float should not be spent casually, however. If furniture delivery slips by more than ten days, as happens when manufacturers change lead times, the furniture path becomes critical.
Third, the 40 working days must fit before the cutover deadline of October 24 with room to spare. Working backward from that date, the project should start the layout approval no later than early August. Starting in late June, as planned, leaves roughly six weeks of buffer for the risks identified in the risk register. The project management standard treats schedule buffers of this kind as a deliberate response to uncertainty rather than padding hidden in individual estimates (Project Management Institute, 2021).
References
Kelley, J. E., Jr., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, eastern joint IRE-AIEE-ACM computer conference (pp. 160-173). Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318
Malcolm, D. G., Roseboom, J. H., Clark, C. E., & Fazar, W. (1959). Application of a technique for research and development program evaluation. Operations Research, 7(5), 646-669. https://doi.org/10.1287/opre.7.5.646
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.
Reading the GCU MGT 440 Topic 4 instructions
The Topic 4 instructions in MGT-440 ask students to calculate a project's critical path. Naming the longest path without showing the calculation will not meet the standard. The assignment rewards a table of activities with durations and predecessors, a three-point estimate where a duration is uncertain, a forward pass for early dates, a backward pass for late dates and float for each activity. Students should identify the critical path and its length, compare it with other paths and explain what the result means for the project, such as where to focus management attention, how to treat float and when the project must start to meet its deadline.
Inside the MGT 440 Topic 4 example
The paper opens with the question the calculation answers. Table 1 lists six activities with durations and predecessors. The three-point estimate for build-out is worked through with the weighted formula and its standard deviation, with an explanation of why the result sits above the most likely value. Table 2 shows the forward pass and Table 3 the backward pass with float. A section identifies the 40-day critical path and the 30-day furniture path, citing the method's origins. The closing section draws three implications: focus on build-out, protect furniture float and start layout approval early enough to keep a buffer.
Where the marks sit in the MGT 440 Topic 4 rubric
Instructors grading the critical path calculation reward working that a reader can follow line by line. Strong papers state every duration and predecessor, show both passes and calculate float correctly for each activity. Credit goes to using a three-point estimate for the most uncertain activity and explaining what the estimate implies. The rubric values interpreting the result, since a critical path matters only for what it tells the project manager to do. The highest band connects the calculation to the deadline and to the risks that could move it. Calculations that skip the backward pass, or name a path without float figures, usually lose marks.
Common MGT 440 Topic 4 mistakes, and how to avoid them
Critical path work can be marked plainly wrong, and the errors are recognizable. A critical path named without forward and backward passes has been guessed, even when the guess happens to be right, because the rubric rewards derivation. Forward passes taking the earlier finish at a merge point understate the project duration, and every later date inherits the mistake. Backward passes taking the later start at a split produce float that does not exist. Calculations that treat the activity with the longest lead time as critical, rather than the longest path, confuse a worrying item with a controlling one, as the ten days of float on furniture ordering shows. Schedules with durations but no stated dependencies cannot be calculated at all. Papers that never test the result miss that a critical path can change.
Get an MGT-440 Topic 4 example written to your instructions
Send the MGT-440 Topic 4 instructions, the rubric for it and the activity list or case data the assignment supplies. We write a custom example to those criteria, with the network drawn, forward and backward passes shown, float computed for every activity and the critical path derived and tested, in 24 to 48 hours. The first one is free.
More MGT 440 papers and BS in Business Management samples
- MGT 440 Topic 1: Project Classification Memo
- MGT 440 Topic 2: Project Charter
- MGT 440 Topic 3: Scope Statement and Change Log
- MGT 440 Topic 5: Fixed Constraint Dq Post
- MGT 440 Topic 6: Risk Register with Triggers
- MGT 440 Topic 7: Earned Value Status Report
- MGT 440 Topic 8: Project Closure Report
- MGT 434 Topic 4: Internal Equity Pay Review
- MGT 420 Topic 4: Group Performance Diagnosis
- MGT 325 Topic 4: Objection Audit
- BUS 317 Topic 4: Break-even Sensitivity Analysis
MGT 440 Topic 4 questions, answered
Is the critical path always the longest path?
Under the standard assumptions, yes: it is the longest sequence of dependent activities through the network, and it sets the shortest possible project duration. Activities on it carry zero total float when the project finish equals the calculated early finish. If a deadline is imposed earlier than that, float turns negative, which signals the schedule cannot be met as drawn.
What is the three-point estimate formula?
The weighted version commonly taught with PERT adds the optimistic estimate, four times the most likely and the pessimistic estimate, then divides by six. The example applies it to build-out, where 15, 19 and 29 days give 20. A simple average of the three is used in some texts instead, so check which one the course expects.
Why does a non-critical activity still matter?
Because float is a buffer, not a permission to ignore the work. Furniture ordering has ten days of float in the example, and a twelve-day supplier delay would make its path the longest and push the finish date out. Near-critical paths deserve monitoring, which is why the example reports float for every activity rather than only for the critical ones.
Where can I find a free MGT 440 Topic 4 sample paper?
The full calculation is here, from the activity table and the three-point estimate to both passes, the critical path and what it means for the move. Share your activity list and a free calculation can be set up for it.
How is build-out estimated in MGT 440 Topic 4?
With the three-point formula: the optimistic 15 days, four times the most likely 19 days and the pessimistic 29 days add to 120, divided by 6, giving 20 days.