Free sample paper for MGT 455 Topic 8
Not the Ironer: A Throughput Recommendation for a Commercial Laundry, Testing Three Investments Against the Dryers That Set Output and the Washers That Would Set It Next
[Author Name]
Colangelo College of Business, Grand Canyon University
MGT-455: Production/Operations Management
Topic 8 Assignment
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Not the Ironer: A Throughput Recommendation for a Commercial Laundry, Testing Three Investments Against the Dryers That Set Output and the Washers That Would Set It Next
The Situation
Summit Linen Services is a composite laundry plant that processes sheets, towels and table linens for roughly 40 hotel and restaurant accounts. It runs two shifts, about 4,800 operating hours a year, and turns away roughly 5,000 pounds of hotel work a day because it cannot process more. Demand for more output therefore exists. The owner has three proposals on the table: a new flatwork ironer for $140,000, an additional large dryer for $60,000 and a set of staging carts at the dryers for $8,000. This recommendation tests each against the laundry's stage capacities. All figures are illustrative.
Stage Capacities
Table 1
Stage Capacities
| Stage | Capacity (pounds per hour) |
|---|---|
| Sorting | 2,400 |
| Washing | 1,900 |
| Drying | 1,600 |
| Ironing | 2,200 |
| Folding | 2,000 |
Table 1 gives each stage's capacity in pounds per hour.
Drying, at 1,600 pounds an hour, is the slowest stage, so it sets the laundry's output. Every other stage can handle more than drying can supply. Washing is the next slowest, at 1,900, which matters because it will become the limit if drying improves. In any process, output is limited by its slowest stage, and investments should be judged by their effect at that stage (Goldratt & Cox, 2004).
The capacities were measured over two weeks of normal operation, using the weight of linen processed at each stage per hour of operating time. They reflect real conditions, including staffing and machine availability, rather than the manufacturers' rated capacities, which are higher.
Proposal One: The Ironer
The ironer is the most expensive proposal and the one the production supervisor favors, because ironing is the most visibly labor-intensive stage and the current ironer is old. But ironing's capacity, 2,200 pounds an hour, already exceeds drying's 1,600. A faster ironer would iron the same 1,600 pounds an hour that the dryers supply and stand idle more of the time. It would add nothing to output. Replacing it may be justified later on grounds of maintenance cost or quality, but not on throughput.
The supervisor's preference is understandable. The ironing room is crowded, loud and the place where delays are most visible, because carts of dried linen wait there. But the carts are waiting for ironers who are already faster than the dryers on average; the crowding comes from uneven arrivals, not from too little ironing capacity.
Proposal Two: An Additional Dryer
An additional large dryer, at $60,000, would raise drying capacity from 1,600 to 2,000 pounds an hour. Output would not rise to 2,000, however, because washing would then become the slowest stage at 1,900. The bottleneck moves from drying to washing. The net gain is therefore 1,900 minus 1,600, or 300 pounds an hour, not 400.
At a contribution of 12 cents per pound, the difference between the price customers pay and the variable cost of processing, 300 additional pounds an hour over 4,800 operating hours is worth 300 times 4,800 times $0.12, or $172,800 a year. The dryer would pay for itself in about four months. Because the laundry turns away about 5,000 pounds a day, there is enough demand to absorb the added output, which works out to about 4,800 pounds a day across two shifts.
Proposal Three: Staging Carts
Drying loses time between loads. When a dryer finishes, an attendant must walk over, unload it, carry the load to ironing and return with the next washed load, during which the dryer sits idle. Observations showed each of the five dryers idle for about six minutes per hour on average waiting to be reloaded. Staging carts, loaded with the next batch of washed linen and parked beside each dryer, would allow an attendant to swap loads in about a minute.
That would recover about five minutes per dryer per hour, raising effective drying capacity by roughly 150 pounds an hour, from 1,600 to 1,750. At 12 cents a pound over 4,800 hours, that is worth about $86,400 a year, for an investment of $8,000. Keeping a bottleneck stage working every available minute is often the cheapest way to raise output, because an hour lost at the bottleneck is an hour lost for the whole system (Hopp & Spearman, 2008).
The carts also change the attendants' work. Instead of walking back and forth with each load, an attendant stages the next load during the dryer's cycle and makes a quick swap when it ends, which is easier on the attendants as well as faster for the dryers.
Combining the Proposals
The carts and the dryer work together. With carts alone, drying rises to 1,750 and remains the bottleneck. With the dryer alone, drying rises to 2,000 but washing limits output at 1,900. With both, drying could reach about 2,190 pounds an hour, but washing still limits the laundry at 1,900. The carts therefore add nothing beyond what the dryer already delivers if both are bought, unless washing is also improved. The order of investment matters.
This is why the order of investment matters more than the list. Buying the dryer first and the carts second would spend $8,000 for no gain, while buying the carts first gives an immediate return and shows management how much drying time was being lost.
Recommendation
The laundry should buy the staging carts now. They cost $8,000, pay back in about five weeks and raise output by about 150 pounds an hour without capital commitment. It should then add the dryer, which raises output to the washing limit of 1,900 pounds an hour, an additional 150 pounds beyond the carts. At that point washing becomes the bottleneck, and the next proposal worth studying is washer capacity, perhaps through faster changeovers between wash formulas. The ironer should be set aside for now; it adds no output while ironing remains faster than the stages feeding it. Capacity decisions are best made with the whole sequence of stages in view, since an improvement at one stage changes where the next constraint appears (Slack et al., 2022).
References
Goldratt, E. M., & Cox, J. (2004). The goal: A process of ongoing improvement (3rd rev. ed.). North River Press.
Hopp, W. J., & Spearman, M. L. (2008). Factory physics (3rd ed.). McGraw-Hill/Irwin.
Slack, N., Brandon-Jones, A., & Burgess, N. (2022). Operations management (10th ed.). Pearson.
What the MGT 455 Topic 8 instructions ask for
The Topic 8 instructions for MGT-455 ask students to recommend how to increase an operation's throughput. Choosing the investment that looks most impressive, or the stage that seems busiest, misses the analysis. The assignment rewards a recommendation that starts from stage capacities, identifies the current bottleneck and the stage that would limit output next, and tests each proposal against them. Students should calculate each proposal's actual gain in output and its value using contribution per unit, consider low-cost ways of keeping the bottleneck busy and recommend a sequence of investments, naming the next constraint to study.
How the MGT-455 Topic 8 example is put together
The recommendation opens with the laundry's demand and three proposals. Table 1 lists five stage capacities, and the paper identifies drying as the bottleneck and washing as the next. The ironer is tested and rejected for throughput purposes. The dryer is tested, its gain capped by washing at 300 pounds an hour and valued at $172,800 a year. Staging carts are tested using observed dryer idle time. A section shows how the carts and dryer interact, and the recommendation orders the investments, sets the ironer aside and names washing as the next constraint. Capacities come from two weeks of measured operation rather than rated figures.
MGT 455 Topic 8 rubric: what Excellent looks like
Instructors grading the throughput recommendation reward capacity figures used to test every proposal. Strong papers identify both the current bottleneck and the next one, and they cap each proposal's gain at whatever stage would then limit output. Credit goes to valuing gains with contribution per unit and operating hours and to considering cheap ways to recover lost time at the bottleneck. The rubric values showing how proposals interact and recommending an order for investment. The highest band names the next constraint to study and draws on operations sources. Recommendations that favor the largest machine without testing its effect on output usually lose points.
MGT 455 Topic 8 help before you submit
Recommendations in the closing topic gain or lose most of their marks on the throughput figure. A proposal justified by how much faster a stage will run, rather than by what the plant as a whole will produce, has measured the wrong thing, and the ironer is the example the course is built to catch. Papers that assume new capacity will be used without checking demand overstate the benefit, since pounds nobody orders contribute nothing. An added dryer credited with its full 400 pounds an hour ignores the washing limit that caps the gain at 300. Options compared on different bases, one by payback, another by labor saved, cannot be ranked. Contribution figures that deduct a share of rent or salaried staff understate what each extra pound earns, while figures that ignore energy and chemicals overstate it.
Get an MGT-455 Topic 8 example written to your instructions
Send the MGT-455 Topic 8 instructions, the final rubric from your classroom and the operation or case data your section assigned. We write a custom example to those criteria, with the capacity table, demand confirmed, each proposal compared on the same basis and the gain in plant output stated as a number, returned in 24 to 48 hours. The first one is free.
More MGT 455 papers and BS in Business Management samples
- MGT 455 Topic 1: Transformation System Paper
- MGT 455 Topic 2: Timed Process Flowchart
- MGT 455 Topic 3: Bottleneck Capacity Calculation
- MGT 455 Topic 4: Cost of Poor Quality Breakdown
- MGT 455 Topic 5: Local Efficiency Dq Post
- MGT 455 Topic 6: Economic Order Quantity Problem
- MGT 455 Topic 7: Forecast Error Scorecard
- MGT 440 Topic 8: Project Closure Report
- MGT 434 Topic 8: Practice Defense Memo
- MGT 420 Topic 8: Work Design Intervention Plan
- BUS 317 Topic 8: Funding Request Memo
MGT 455 Topic 8 questions, answered
What counts as throughput in a recommendation?
The rate at which the operation produces output that is actually sold, measured in units per hour, per day or per year. It is different from the speed of any single stage. In the laundry example, throughput is the pounds leaving the plant for paying customers, so a change that speeds ironing without speeding drying leaves it exactly where it was.
Why use contribution rather than revenue to value the gain?
Because revenue overstates what an extra unit earns. Contribution subtracts the costs that rise with each unit, such as chemicals, water and energy in a laundry, and leaves what is available to cover fixed costs and profit. Rent and salaried staff do not change when output rises, so loading them into the per-unit figure would understate the gain.
Should the recommendation include more than one option?
Most closing rubrics reward a comparison, because a single proposal gives the reader nothing to weigh it against. Including a proposal that fails, such as the ironer, also shows the writer tested an obvious idea and rejected it on the numbers. A strong version closes on a sequence and a trigger for the next step, rather than on a single purchase.
Where can I find a free MGT 455 Topic 8 sample paper?
The laundry recommendation is above in full, with the capacity table, each proposal tested, how they combine and the order of investment. Tell us your stages and their capacities and we will draft a free recommendation for them.
Why does the ironer add nothing in MGT 455 Topic 8?
Ironing already handles 2,200 pounds an hour while drying supplies only 1,600. A faster ironer would iron the same 1,600 pounds and simply stand idle more often.