MGT 641 Topic 7 agile adoption behavior audit example

Agile Project Management Grand Canyon University Free custom sample in 24 to 48h

This MGT 641 Topic 7 sample paper audits a composite credit union's first year of sprints on its lending app by behavior instead of by ceremonies held. It sits in GCU MGT 641, Agile Project Management, catalog code MGT-641, within the Grand Canyon University MBA with an Emphasis in Project Management. Every event took place for twelve months, yet members still got releases quarterly because the change board approves production changes only in a quarterly window. Seven of nine mid-year requests went through the vendor's change process, five of seven developers were replaced, and 38 percent of stories waited on another group. Lead time averaged 97 days, and most of it passed in queues outside the team.

CourseMGT 641 Agile Project Management
TopicTopic 7
Paper typeAdoption behavior audit
LengthAbout 1,140 words, 7 pages
FormatAPA 7 student paper
SchoolGrand Canyon University (GCU)
ProgramMBA
UpdatedOctober 2026

Free sample paper for MGT 641 Topic 7

1

Every Ceremony Held, Few Conditions Met: A Behavior Audit of a Credit Union's First Year of Sprints on Its Member Lending App

[Author Name]

Colangelo College of Business, Grand Canyon University

MGT-641: Agile Project Management

Topic 7 Assignment

[Instructor Name]

[Date]

The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.

What this page is doingThe title concedes the ceremonies and names what the audit actually measures. Sagebrook Community Credit Union and all figures are an illustrative composite; the sources are real.
2

Every Ceremony Held, Few Conditions Met: A Behavior Audit of a Credit Union's First Year of Sprints on Its Member Lending App

What the Adoption Promised

Twelve months ago Sagebrook Community Credit Union moved its member lending app team to two-week sprints. The launch memo named two goals: release improvements to members faster, and respond to what members and lending staff ask for during the year rather than waiting for the next annual plan. This audit tests those two claims. It does not test whether the team follows Scrum's rules, because the answer to that question is already known and, as the next section explains, settles nothing.

What this page is doingThe audit starts from the adoption's own stated goals, so its verdict measures the claims the organization made.
3

The Ceremonies, Confirmed and Set Aside

Every planned sprint event took place for twelve months. Planning, daily meetings, reviews and retrospectives were all held on schedule, and attendance was good. That record proves the calendar was kept. It does not show whether anything about how Sagebrook builds and releases software changed. Conboy (2009) argues that agility should be judged by an organization's ability to create, embrace and learn from change, and by the economy and speed with which it does so, not by the presence of named practices. The audit follows that view and measures four behaviors instead.

Four Behaviors Measured

Table 1

Four Adoption Behaviors After Twelve Months, Illustrative

BehaviorMeasureSourceFinding
Release frequencyProduction releases to membersDeployment recordsFour, one per quarter
Scope flexibilityMid-year requests absorbed into a sprintRequest log2 of 9
Team stabilityDevelopers replaced during the yearVendor staffing reports5 of 7
Team independenceStories that waited on another groupSprint recordsAbout 38 percent

Table 1 lists each behavior, the measure used, the source and the finding. The figures are illustrative.

Release Frequency

Members received new features four times in the year, the same as before the adoption. The cause is outside the team. Sagebrook's change advisory board approves production changes only in a quarterly window, so the work of six two-week sprints joins a queue and waits for that window. Short sprints have produced finished increments faster; they have not reached members faster. Forsgren et al. (2018) identify deployment frequency and lead time for changes as two of the four measures most closely linked to delivery performance, and on both Sagebrook is where it was a year ago.

What this page is doingThe section separates sprint length from release frequency, which is the distinction that cancels most of the adoption's promised benefit.
4

Scope Flexibility

Lending staff made nine requests during the year that were not in the original plan, including a co-borrower field and a change to how declined applications are explained. Two were absorbed into a sprint. The other seven went through the vendor's change request process, which required a priced amendment and approval from the contracts office, and took an average of seven weeks to reach the backlog. The contract still fixes scope, so the team can respond to change only when the change is small enough to avoid the contract.

Team Stability

The vendor replaced five of its seven developers during the year, rotating them to other clients. Velocity never settled, ranging from 14 to 29 points a sprint, and each new developer spent most of a sprint learning the lending rules and the core system connections. Nothing in the contract or the adoption plan treated a stable team as a requirement, although the method depends on one. Teams that keep the same people build shared knowledge of the product and of each other, and that knowledge is what makes estimates reliable and handoffs short. Every rotation reset part of it. The two developers who stayed all year now hold most of the knowledge of the lending rules, which concentrates risk in two people the credit union does not employ.

Team Independence

About 38 percent of completed stories waited on another group before they could be finished, chiefly the core banking integration team and the compliance reviewers. The team cannot finish most member-facing work alone, so its sprint plans depend on queues it does not control.

The figure has not improved during the year. In the first quarter 41 percent of stories waited on another group, and in the last quarter 36 percent did, a difference small enough to come from the mix of work. Compliance waits did fall after the reviewers began attending refinement sessions every other sprint, which shows that the dependency can be shortened when someone decides to. Integration waits did not fall, because no comparable step was taken there. The team's members describe planning around these waits as the hardest part of their work, and several stories each quarter were started, blocked and then set aside, which also explains part of the gap between work begun and work finished.

Lead Time Traced

Lead time from an approved request to a member-facing release averaged 97 days. Three sample requests show where those days went. The co-borrower field spent 6 days in refinement, 10 in a sprint, 12 waiting on integration and 64 waiting for the release window, a total of 92 days. A change to the payment calendar spent 4 days in refinement, 10 in a sprint and 81 waiting for release. The declined-application explanation spent 49 days in the change request process, 10 in a sprint and 55 waiting for release. In each case the team's own work took 10 days, and most of the elapsed time passed in queues outside it.

What this page is doingTracing three requests end to end gives the 97-day average concrete cases and shows where the time actually goes.
5

The Pattern

Taken together, the findings describe what Theocharis et al. (2015) call Water-Scrum-Fall: agile practices inside the development team, surrounded by traditional upfront contracting at one end and traditional release control at the other. Their study found this hybrid common in practice. At Sagebrook it was not chosen deliberately; it is what remained when sprints were introduced and nothing around them changed.

The Too-Soon Defense

The project sponsor argues that a year is too short for behavior to change. The argument holds for some things. Retrospective habits and estimation consistency often improve with time, and a second year might show gains there. But the three largest findings will not move with time. A quarterly release window, a fixed-scope contract and a vendor free to rotate developers are policies, and each will produce the same result in year two unless someone changes it.

What this page is doingThe defense is answered by separating what time might improve from what only a policy change can fix.
6

Recommendations

Each missing condition is assigned to the executive who controls it. The chief information officer should ask the change advisory board to approve low-risk releases monthly, with a lighter review for changes that do not touch core banking. The chief financial officer should renegotiate the vendor contract to price a team's capacity rather than a fixed scope, so lending requests enter the backlog directly. The vendor management director should add a clause holding named developers on the team for at least a year. The integration manager should give the lending app team access to make routine changes itself. The audit should be repeated in twelve months using the same four measures and the same lead-time trace.

What this page is doingOne recommendation per absent condition, each with an owner, keeps the audit from ending on general advice.
7

References

Conboy, K. (2009). Agility from first principles: Reconstructing the concept of agility in information systems development. Information Systems Research, 20(3), 329-354. https://doi.org/10.1287/isre.1090.0236

Forsgren, N., Humble, J., & Kim, G. (2018). Accelerate: The science of lean software and DevOps: Building and scaling high performing technology organizations. IT Revolution Press.

Theocharis, G., Kuhrmann, M., Münch, J., & Diebold, P. (2015). Is Water-Scrum-Fall reality? On the use of agile and traditional development practices. In P. Abrahamsson, L. Corral, M. Oivo, & B. Russo (Eds.), Product-focused software process improvement (pp. 149-166). Springer. https://doi.org/10.1007/978-3-319-26844-6_11

What the MGT 641 Topic 7 instructions ask for

Topic 7 in MGT-641 asks whether an agile adoption has actually changed how an organization delivers. Counting meetings held or rising velocity does not answer that question. A paper meets the brief when it starts from the adoption's stated goals, chooses behavioral measures such as release frequency, scope flexibility, team stability and independence, and finds evidence for each in records rather than opinions. Graduate students should draw on research about agility and delivery performance, trace lead time through real requests to show where time is lost, and name the pattern the findings describe. The audit should address the argument that it is too soon to judge and end with recommendations tied to the executives who control each missing condition.

How this MGT 641 Topic 7 example is built

The finished audit concedes the calendar at once: every planned sprint event took place for twelve months. It then measures four behaviors, numbers illustrative. Releases to members still happen quarterly, because the change advisory board approves production changes only in a quarterly window, so two-week sprints feed a three-month queue. Of nine mid-year requests from lending staff, two were absorbed into a sprint and seven went through the vendor's change request process, which shows scope still governed by contract. The vendor replaced five of the seven developers during the year, so velocity never settled. About 38 percent of completed stories waited on another group, chiefly the core banking integration team. Lead time from an approved request to a member-facing release averaged 97 days. Its conclusion is that the practices were installed and the conditions were not.

MGT 641 Topic 7 rubric: what Excellent looks like

Graders award an Excellent audit for measuring outcomes and conditions rather than ritual. The rubric rewards papers that concede the ceremonies briefly and then set them aside, choose measures with clear sources, and connect each finding to its cause, such as the quarterly release window that cancels the benefit of short sprints. Credit goes to tracing several requests end to end so the lead-time figure has concrete cases. Strong papers treat developer turnover as a condition the method depends on and recognize the water-scrum-fall pattern. The highest band separates what time might improve from what only a policy change will fix, and assigns one recommendation per missing condition to the executive who owns it.

MGT 641 Topic 7 help before you submit

An adoption audit that reports full attendance and a satisfied team has measured the ritual this topic warns against. Papers counting velocity growth as evidence of success confuse a team's own unit with a result members can feel, and velocity can rise while nothing reaches production faster. Missing the release window is the costliest oversight in this case, since it cancels the benefit of short sprints however well they run. Treating developer turnover as a staffing footnote overlooks a condition the method depends on. Blaming the team for slow lead time ignores that most of the 97 days pass in queues it does not control. The too-soon defense deserves a direct answer as well, one that separates what a second year might improve from what only a changed contract, board or staffing policy could.

Get an MGT-641 Topic 7 example written to your instructions

Send the MGT-641 Topic 7 instructions, the rubric for it and any adoption goals, delivery data or case the assignment supplies. A custom example is written to those requirements, with ceremonies set aside, four behaviors measured from records, lead time traced end to end and each missing condition assigned an owner, returned in 24 to 48 hours. The first one is free.

More MGT 641 papers and MBA samples

MGT 641 Topic 7 questions, answered

What measures show whether an agile adoption is working?

Measures of outcome and flow rather than activity. Forsgren, Humble and Kim's research on software delivery, reported in Accelerate, uses deployment frequency, lead time for changes, change failure rate and time to restore service. The example adds two condition checks the course emphasizes: whether scope actually changed in response to learning, and whether the team stayed together long enough to become predictable.

Why not measure velocity?

Velocity helps a team forecast its own work, but it is a relative unit the team controls, and it can rise through re-estimation without anything changing for users. Used as an adoption measure, it invites inflation. The example uses it only to show instability after developer turnover, and relies on release and lead time records for the judgment about whether members are served faster.

Is a year long enough to judge an adoption?

Long enough to judge conditions, if not every outcome. Some practices do improve with time, such as retrospective follow-through or estimation consistency. A quarterly release window, a fixed-scope contract and a rotating vendor team will not improve by waiting, because nothing in the sprint cycle can change them. The example separates the two groups and asks the credit union to act on the second.

Where can I find a free MGT 641 Topic 7 sample paper?

The full first-year adoption audit is on this page: goals, the ceremonies set aside, the four behaviors, the 97-day lead-time trace, the pattern, the too-soon defense and the recommendations. Tell us about your organization's adoption and a free audit can be written from its records.

Why did releases stay quarterly in MGT 641 Topic 7?

The change advisory board approves production changes only in a quarterly window, so increments from six two-week sprints wait together for release. The team finished work faster, but members did not receive it any sooner.