Slack Is Planning Information: Scheduling a Polishing Cell Installation, Finding the Near-Critical Path and Using Slack to Protect the Bottleneck
[Author Name]
Colangelo College of Business, Grand Canyon University
MGT-655: Operations Management
Topic 7 Schedule Slack Analysis
[Instructor Name]
[Date]
The organization, setting and figures below are a composite written as a model document. No real employer, client, colleague or patient is described.
Slack Is Planning Information: Scheduling a Polishing Cell Installation, Finding the Near-Critical Path and Using Slack to Protect the Bottleneck
The Project and Its Activities
A composite food-service equipment plant is installing an automated polishing cell to relieve its bottleneck. The project has eight activities, listed with their durations in working days and their predecessors. Equipment must be ordered (A, 20 days). The floor and utilities must be prepared (B, 8 days). An operator must be hired and trained (C, 15 days). The equipment is installed once it arrives and the floor is ready (D, 5 days, after A and B). Fixture programs are written once the equipment specifications are confirmed on delivery (E, 6 days, after A). Test runs follow installation and programming (F, 4 days, after D and E). The operator is certified on the installed equipment (G, 3 days, after C and D). Production ramps up after testing and certification (H, 5 days, after F and G).
Early and Late Times, Both Directions
A pass forward through the network yields the soonest each activity can begin and end; a pass backward from the finish yields the latest each can begin and end without pushing out completion (Kelley, 1961). Subtracting the earliest start from the latest start gives total slack, a measure Heizer et al. (2020) treat as the core planning output. The project takes 35 working days.
Table 1
Schedule Times and Slack in Working Days
| Activity | Days | Soonest start | Soonest finish | Latest start | Latest finish | Total slack | Free slack |
|---|---|---|---|---|---|---|---|
| A Order equipment | 20 | 0 | 20 | 0 | 20 | 0 | 0 |
| B Floor and utilities | 8 | 0 | 8 | 13 | 21 | 13 | 12 |
| C Hire and train operator | 15 | 0 | 15 | 12 | 27 | 12 | 10 |
| D Install equipment | 5 | 20 | 25 | 21 | 26 | 1 | 0 |
| E Program fixtures | 6 | 20 | 26 | 20 | 26 | 0 | 0 |
| F Test runs | 4 | 26 | 30 | 26 | 30 | 0 | 0 |
| G Certify operator | 3 | 25 | 28 | 27 | 30 | 2 | 2 |
| H Ramp production | 5 | 30 | 35 | 30 | 35 | 0 | 0 |
Total and Free Slack
Total slack is how long an activity can be delayed without delaying the project. Free slack is how long it can be delayed without delaying any successor's earliest start. The difference matters when slack is shared along a path. Floor preparation (B) has 13 days of total slack but 12 of free slack: it can slip 12 days without touching anything, but a thirteenth day would use the single day of slack that installation (D) also depends on, so D could no longer slip at all. Operator training (C) has 12 days of total slack and 10 of free slack, for the same reason: two of its days are shared with certification (G). A planner who delays an activity within its total slack but beyond its free slack can unexpectedly block a successor that had been counting on the same room (Meredith et al., 2017).
The Critical Path and the Near-Critical One
The critical path is the chain of zero-slack activities: order equipment, program fixtures, test runs and ramp production, A, E, F and H, 35 days. A second path, A, D, F and H, takes 34 days and has one day of slack. That near-critical path deserves almost as much attention as the critical one, because a one-day slip in installation makes it critical too. Most unexpected schedule slippage comes from near-critical paths that were not watched.
Using Slack to Reallocate a Constrained Resource
The slack figures answer a practical question. Training the new operator (C) requires the plant's senior polisher as trainer for most of its fifteen days, and the senior polisher is the person who runs the current bottleneck. Every hour the polisher spends training is an hour of lost output for the whole plant. Because C has 12 days of total slack and 10 of free slack, training can start as late as day 10 without affecting anything else. The plan therefore schedules training to begin on day 10 and to run during the plant's lighter second week of the month, rather than at the project's start during a heavy order period. Slack has been used to move effort away from the constraint at the time it is most needed.
A Reallocation That Would Backfire
The slack figures also show what not to do. The project manager proposed moving the plant's controls technician from installation (D) to fixture programming (E), which would shorten programming from 6 days to 4. That would cut the A, E, F, H path to 33 days, but the A, D, F, H path, at 34 days, would become critical, and if installation slowed by even one day without the technician, the project would take 35 days again. The move would save at most one day and could save none. Without the slack figures, the proposal looked like a two-day gain.
Monitoring Slack During the Project
Slack is consumed as the project runs, and the schedule should be treated as a living plan. The project manager should update earliest and latest times weekly and report the slack remaining on installation and certification, the two activities whose slack is small. If installation's single day of slack is used, the project has two critical paths, and any further delay on either will move the completion date. The plant's customers have been promised added capacity in seven weeks, so the 35-day schedule leaves about five working days of margin against that promise; that margin should be reported alongside the slack figures each week, so that the plant can warn customers early if it begins to shrink.
Conclusion
The critical path, A, E, F and H, sets the project at 35 working days, but it is not the only information the calculation produces. A near-critical path through installation has a single day of slack and must be watched as closely as the critical one. Free and total slack differ for floor preparation and operator training, and the difference determines how far each can be moved without disturbing a successor. Used deliberately, the slack on training lets the plant keep its senior polisher on the bottleneck during a heavy period, and the slack figures expose a proposed reallocation that would have gained nothing. Reported weekly, the remaining slack tells the project manager where the next delay would hurt.
References
Heizer, J., Render, B., & Munson, C. (2020). Operations management: Sustainability and supply chain management (13th ed.). Pearson.
Kelley, J. E. (1961). Critical-path planning and scheduling: Mathematical basis. Operations Research, 9(3), 296-320. https://doi.org/10.1287/opre.9.3.296
Meredith, J. R., Shafer, S. M., & Mantel, S. J., Jr. (2017). Project management: A strategic managerial approach (10th ed.). Wiley.
What the MGT 655 Topic 7 instructions ask for
The Topic 7 assignment in MGT-655 asks MBA students to analyze schedule slack. Strong analyses list every activity with its duration and predecessors, compute early and late times in both directions and derive total and free slack for each. Students should identify the critical path and any near-critical path, use slack to reallocate a constrained resource and describe how slack will be monitored as the project runs. Total and free slack should be distinguished with an example of where the difference matters. Reallocations should be checked against slack before they are made, since moving people without reference to slack can create a new critical path.
How the MGT-655 Topic 7 example is put together
The finished example treats slack as the useful output. Every activity carries its total slack, and the example distinguishes that from free slack, since an activity can be delayed without moving the project end and still push a successor. Zero slack activities define the critical path as a consequence rather than as the object of the exercise. Resource allocation is then made from the slack figures: people can be moved off activities with room and onto activities with none, which is the practical use most schedules never make of the calculation. The example also shows slack shrinking as the project progresses, since delays consume it and a path with little left is worth watching.
Reading the MGT 655 Topic 7 rubric
Faculty reward slack used, not just computed. An Excellent paper tables eight activities with early and late times, total slack and free slack, following Kelley's method and Heizer and colleagues. Credit goes to explaining shared slack between floor preparation and installation, with Meredith and colleagues. The rubric values a near-critical path one day behind. Strong papers schedule training to protect the bottleneck operator. Top marks go to exposing a reallocation that would have saved nothing and weekly slack reporting. Credit also goes to reporting the margin between the schedule and the date promised to customers alongside the slack figures. Faculty also value schedules treated as living plans, updated weekly as slack is consumed.
MGT 655 Topic 7 help: mistakes that cost marks
Reporting the critical path and nothing else wastes the calculation, since the slack figures for every other activity are already computed and carry the planning information. A second failure is ignoring near critical paths, which become critical after a small delay and are the usual source of unexpected schedule slippage. Papers lose marks for confusing total and free slack, which produces plans where an activity is delayed within its total slack and unexpectedly blocks a successor. Reallocating resources without reference to slack moves people from where they were needed to where they were not. Schedules presented as fixed, with no monitoring plan, ignore that slack is consumed as work proceeds.
Get an MGT-655 Topic 7 example written to your instructions
Send the MGT-655 Topic 7 problems and the rubric your classroom posts, with the activity list and resource constraints your section supplied. We write a custom example to those criteria, with slack computed throughout, total distinguished from free, near critical paths flagged and resources reallocated using the figures, in 24 to 48 hours. The first is free.
More MGT 655 papers and MBA samples
- MGT 655 Topic 1: Operations Strategy Analysis
- MGT 655 Topic 2: Forecast Error Analysis
- MGT 655 Topic 3: Process and Capacity Analysis
- MGT 655 Topic 4: Control Chart Interpretation
- MGT 655 Topic 5: Supply Chain Risk Analysis
- MGT 655 Topic 6: Inventory Policy Analysis
- MGT 655 Topic 8: Lean Process Improvement
- MGT 641 Topic 7: Agile Adoption Behavior Audit
- MGT 640 Topic 7: Benefits Realization Review
- MGT 605 Topic 7: Team and Change Analysis
- ACC 502 Topic 7: Cash Flow Statement Build
MGT 655 Topic 7 questions, answered
What is the difference between total and free slack?
Total slack is how long an activity can be delayed without moving the project finish date. Free slack is how long it can be delayed without moving any successor. An activity can have several days of total slack and none free, meaning any delay immediately pushes the next task even though the end date holds. That distinction matters whenever somebody else is waiting on a handover.
Why watch near critical paths?
Because they become critical quickly. A path with three days of slack absorbs a three day delay and then constrains the finish date exactly like the original critical path, and teams focused entirely on the critical chain never see it coming. Listing paths by remaining slack, rather than only naming the critical one, is what makes a schedule manageable rather than merely correct.
How does slack help with resources?
It tells you where you can take from safely. If a specialist is needed on a zero slack activity and is currently assigned to one with a week of room, moving them delays nothing and protects the finish date. Schedules that compute the critical path and stop have the information needed to make those decisions sitting unused in the calculation.
Where can I find a free MGT 655 Topic 7 sample paper?
The slack analysis is shown here complete: the activities, early and late times, total and free slack, the critical and near-critical paths, a reallocation, one that would backfire, monitoring and the conclusion. List your project's activities and durations and the schedule follows free.
Why watch the near-critical path in MGT 655 Topic 7?
Installation has a single day of slack. If it slips one day, its path becomes critical too, and any further delay moves the completion date.