MGT 640 Topic 1 strategic initiative triage memo example

Fundamentals of Project Management Grand Canyon University Free custom sample in 24 to 48h

This MGT 640 Topic 1 sample paper is a triage memo deciding which of six strategic initiatives at a composite regional insurer deserve the cost of a funded project. It was prepared for GCU MGT 640, Fundamentals of Project Management, catalog code MGT-640, in the Grand Canyon University MBA with an Emphasis in Project Management. Instead of defining a project and sorting the list, the memo first prices the project vehicle itself, a sponsor, a manager, a steering group and benefits tracking, at roughly 12 to 15 percent of direct cost. Four conditions then decide whether that premium is worth paying. Two initiatives pass, two stay with operating managers, one splits, and the board's favorite policyholder app is declined.

CourseMGT 640 Fundamentals of Project Management
TopicTopic 1
Paper typeInitiative triage memo
LengthAbout 820 words, 3 pages
FormatMemo with APA 7 references
SchoolGrand Canyon University (GCU)
ProgramMBA
UpdatedOctober 2026

Free sample paper for MGT 640 Topic 1

1

Memorandum

To: Executive Committee, Larkspur Mutual Insurance

From: Enterprise Project Management Office

Date: [Date]

Re: Which of six proposed initiatives should be run as formal projects

 

The Premium a Project Costs

The executive committee has asked the enterprise project management office which of six proposed initiatives should be run as formal projects next year. Before answering, this memo prices the project vehicle itself, because running an initiative as a project is not free. At Larkspur Mutual, an illustrative mid-sized insurer writing auto, home and commercial policies, every formal project carries a sponsor's time, a dedicated project manager, a steering group that meets monthly and a benefits tracking process that continues after delivery. On the insurer's recent projects, those elements have added roughly 12 to 15 percent to an initiative's direct cost. All figures are illustrative.

That premium is worth paying when the structure solves a problem the line organization cannot solve on its own. When it does not, the same work is cheaper and often faster in the hands of the operating manager who already owns it. Projects exist to deliver change that ongoing operations are not set up to deliver (Project Management Institute, 2021).

What this page is doingThe memo prices the project structure before applying any test, which turns a classification question into a cost-benefit question.
2

Four Conditions

An initiative should be run as a formal project only if it meets all four conditions below.

1. The change crosses functions that no single manager controls, so coordination needs authority above any one department.

2. It needs one-time funding above what an operating budget can absorb.

3. It builds a new capability rather than improving an existing one.

4. It carries a benefit that must be tracked on its own, because the business case depends on it and no existing measure would show it.

The fourth condition matters more than it is usually given credit for. Projects that deliver outputs but never track whether the expected benefits arrive tend to be judged on time and budget alone, and their business cases are never tested (Serra & Kunc, 2015).

The Six Initiatives

Table 1

Six Initiatives Against Four Conditions

InitiativeCrosses functions?One-time funding above budget?Builds new capability?Benefit tracked on its own?Verdict
Retire the legacy policy administration systemYes: underwriting, billing, claims, ITYes: about $14MYesYes: operating cost and time to launch productsProject
Enter a new state for homeowners coverageYes: actuarial, legal, distribution, claimsYes: about $3MYesYes: premium written in the new stateProject
Improve service center call handlingNo: service center onlyNoNo: improves existingNo: existing call metricsOperations
Clear the subrogation backlogNo: claims recovery unitNo: overtime and temporary staffNoNo: recovery dollars already trackedOperations
Launch a branded policyholder appYesYes: about $1.8MPartlyNo: no benefit the case can nameDeclined
Upgrade agency commission statementsPartly: finance, distributionNoNoNoOperations

Table 1 applies the four conditions.

Why Each Verdict

Retiring the legacy policy system passes all four conditions clearly. It touches every function that writes or services a policy, costs far more than any operating budget, replaces an aging platform with new capability and promises benefits, lower operating cost and faster product launches, that will not show up in any existing report unless tracked deliberately. Entering a new state for homeowners coverage is similar on a smaller scale: actuarial, legal, distribution and claims must all prepare, and premium written in the new state is the benefit to track.

Service center call handling and the subrogation backlog both fail the first condition. Each sits within one manager's control, uses that manager's budget and is measured by metrics the insurer already reports. Running either as a formal project would add the premium without adding authority or visibility the manager lacks. The commission statement upgrade is partly cross-functional but small enough for finance and distribution to handle together.

The branded policyholder app is popular with the board, and it meets the first two conditions. It fails the fourth: its proposal names no benefit beyond general customer engagement, offers no measure and gives no estimate of how many policyholders would use it or what they would do differently. A project with no trackable benefit cannot be judged after it is delivered, and the premium would buy coordination for an outcome nobody has defined. The office recommends declining it for now and inviting the sponsor to return with a stated benefit, such as reduced service calls or higher retention, and a way to measure it.

What this page is doingThe memo declines the board's favorite initiative on the one condition it fails and tells its sponsor what would change the answer.
3

Recommendation

The office recommends chartering two projects next year, the legacy system retirement and the new state entry, each with a sponsor, project manager, steering group and benefits tracking. The service center and subrogation improvements and the commission statement upgrade should stay with their operating managers, with progress reported through normal management channels. The policyholder app should be declined until its sponsor can state and measure the benefit it is expected to deliver. Concentrating the project structure where it adds most keeps scarce project managers and steering time for the work that needs them (Kerzner, 2017).

References

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). Project Management Institute.

Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on project success and on the execution of business strategies. International Journal of Project Management, 33(1), 53-66. https://doi.org/10.1016/j.ijproman.2014.03.011

Reading the GCU MGT 640 Topic 1 instructions

Topic 1 in MGT-640 asks graduate students to look at project management from the level of the whole organization, before any single schedule or charter exists. The prompt is about deciding when a change should become a project at all, and how that decision connects to strategy. A memo meets the brief when it sets explicit criteria, applies them to a realistic list of proposed initiatives and explains each verdict in business terms. Students are expected to draw on the project, program and portfolio literature, to show that the project form carries governance costs, and to recognize that some changes are better absorbed by line management. The recommendation should give each approved initiative an accountable sponsor and a strategic objective it serves.

How the MGT-640 Topic 1 example is put together

The finished memo treats a project as an expensive instrument that has to earn its use. It prices the vehicle first, labeled illustrative: a sponsor's time, a project manager, a steering group and benefits tracking add roughly 12 to 15 percent to any initiative's direct cost. Six initiatives are then tested against four conditions for paying that premium: the change crosses functions no single manager controls, needs one-time funding above an operating budget, builds a capability rather than improving an existing one, and carries a benefit that must be tracked on its own. Retiring the legacy policy system and entering a new state for homeowners coverage pass all four. Service center call handling and the subrogation backlog stay with their operating managers. A branded policyholder app, popular with the board, is declined because no strategic objective needs it.

MGT 640 Topic 1 rubric: what Excellent looks like

The rubric for this memo puts its weight on judgment rather than definitions. An Excellent memo states its tests before applying them, so a reader can see why each initiative landed where it did, and it treats the cost of project governance as real money instead of a formality. Graders look for verdicts that link each initiative to a named strategic objective, and for the discipline to decline one that has support but no objective behind it. Credit also goes to handling the mixed case honestly, splitting an initiative into the part that needs a charter and the part a manager can run. Sources from portfolio management research and the published standards support the argument, and the writing reads as a memo to executives, short and direct.

MGT 640 Topic 1 help: mistakes that cost marks

Memos lose the most here by chartering everything, which spends governance on work the line could absorb and delays changes that needed only a manager's decision. A paper defining a project as temporary and unique, then classifying the six, repeats the introductory course and never asks what the vehicle costs. Memos with no link to strategy approve whatever has a sponsor, and the declined app is where a marker looks for that discipline. Leaving the split case whole, either all project or all operations, misses that one initiative can hold both. Graduate papers are expected to defend each verdict against the obvious alternative, here the COO's preference to charter all six. Approved projects with no sponsor or objective attached have been classified without being given anyone to answer for them.

Get an MGT-640 Topic 1 example written to your instructions

Send the MGT-640 Topic 1 instructions, the rubric for your section and any strategy, initiative list or organization the assignment supplies. A custom example comes back in 24 to 48 hours, with the project vehicle priced, conditions for using it stated, each initiative sorted and defended, the split case handled and every approved project tied to an objective. The first one is free.

More MGT 640 papers and MBA samples

MGT 640 Topic 1 questions, answered

What separates this from classifying work as a project or an operation?

An introductory course asks whether a piece of work meets the definition of a project. This memo asks whether a change is worth the cost of running it as one, given what the organization is trying to achieve. The question moves from definition to economics and strategy, so the memo prices the vehicle before sorting anything and declines one initiative outright.

Why not run all six initiatives as projects?

Because the vehicle has a cost and a speed penalty. Chartering the subrogation backlog would add a sponsor, a steering group and reporting to work the claims recovery manager can simply start, and the backlog would wait for approval. The memo defends its verdicts against the COO's instinct to charter everything by showing what each extra project would consume in governance time.

Which sources suit this topic at graduate level?

The strategy execution and portfolio management literature, including the published portfolio and program standards, and work on projects as temporary organizations, where Lundin and Soderholm are often cited. Use them to support the argument that a project is a governance choice with costs, not as definitions to recite. The course text and your instructor's preferences come first.

Where can I find a free MGT 640 Topic 1 sample paper?

The insurer triage memo appears on this page in full, from the price of the project vehicle to the four conditions, the six verdicts and the recommendation to charter two projects. Tell us which initiatives your organization is weighing and we can draft a free memo around that list.

Which initiatives become projects in MGT 640 Topic 1?

Two pass all four conditions: retiring the legacy policy system and entering a new state for homeowners coverage. Call handling and the subrogation backlog stay with operating managers, and the branded app is declined because no strategic objective requires it.